Technical guidelines for connection of power generating plants
Power generating plants must comply with the technical requirements which the DSOs and Energinet have published in accordance with the Commission Regulation (EU) 2016/631 – Requirements for Generators (RfG) and The Danish Electricity Supply Act (Elforsyningsloven). Green Power Denmark has written guidelines which gather all of the requirements for connecting power generating plants to Danish distribution networks. The guidelines can be found below.
Technical guidelines
Annex’ for guide for connection of power generation plants to the low voltage grid
Annex’ for guide for connection of power generation plants to the medium- and high voltage grid
Declaration of Conformity
The Declaration of Conformity aims to confirm that the applicant is familiar with Energinet's validation method for RoCoF and that the unit complies with the requirement for Rate of Change of Frequency robustness (RoCoF)
Find this information in Danish